Ofgem wants data centre developers to provide stronger evidence that projects are commercially credible, technically viable and progressing towards delivery. Its proposals include a substantial commitment fee and new milestones covering customers, finance and electrical equipment procurement.
Britain’s data centre pipeline has expanded faster than the electricity connections system can comfortably accommodate.
Ofgem reports that contracted demand connection offers across Great Britain increased from 41GW in November 2024 to 125GW in June 2025. Its consultation document identifies approximately 73GW across around 315 data centre projects, while the accompanying press release uses the broader figure of “at least 80GW”. The precise reason for the difference between the two figures is not explained.
Not all this capacity is expected to be built or used. A connection offer represents capacity requested from the network, rather than an operational data centre consuming electricity.
Ofgem is therefore consulting on proposals designed to identify projects with credible evidence of delivery and remove developments that fail to progress.
The consultation opened on 29 July 2026 and closes on 16 September 2026. The measures remain proposals and are not currently in force. Ofgem expects to make decisions later in 2026.
| Measure | Proposed application | What developers may need to provide | Possible consequence |
|---|---|---|---|
| Commitment fee | Qualifying data centre projects of 40MW or more | Financial security of £237,500 to £712,500 per MW | Fee could be forfeited if capacity is cancelled, reduced or changed from data centre use |
| Early project milestone | Data centres with at least 10MW rated IT load | Chosen operating pathway and initial evidence of a prospective computing customer | Removal from the connections queue |
| Procurement milestone | Data centres with at least 10MW rated IT load | Evidence of orders or commitments for long-lead equipment | Removal from the connections queue |
| Financial and technical milestone | Data centres with at least 10MW rated IT load | Financial support, recognised technical evidence and, for some projects, binding customer commitments | Removal from the connections queue |
These thresholds, fee levels and requirements remain subject to consultation.
Demand for cloud computing, artificial intelligence, data storage and digital services is supporting the development of larger and more electricity-intensive facilities.
The UK Government’s Compute Roadmap set an ambition for at least 6GW of AI-capable data centre capacity by 2030. Other projections vary considerably but consistently point towards increasing electricity demand.
NESO’s Future Energy Scenarios 2025 estimated that data centre electricity consumption in Great Britain could rise from 7.6TWh in 2024 to between 20TWh and 41TWh by 2035. Oxford Economics separately projected UK consumption rising from 5TWh in 2023 to 26.2TWh in 2030. Differences in geography, definitions and assumptions explain some of the variation between forecasts.
Developers also have sound commercial reasons for applying for electricity capacity early. Grid access can influence:
However, the volume of contracted capacity now extends considerably beyond what is likely to be completed within current timescales.
Ofgem’s consultation identifies data centre connection requests ranging from 1MW to 1,500MW. It also reports that at least 9GW of capacity changed classification from battery storage to data centre use between May 2024 and August 2025. Ofgem does not state how many individual projects were involved or whether those developments will proceed.
“Power is now the primary constraint.”
Huw Owen, Chief Executive Officer, Ark Data Centres, February 2026.
No.
The figure represents connection capacity associated with projects seeking or holding offers. It does not mean every project will be constructed or that completed facilities would use 80GW simultaneously.
Several definitions matter:
| Term | What it means |
|---|---|
| Connection capacity | The maximum electrical capacity requested or agreed for a development |
| Rated IT load | The power allocated specifically to computing equipment |
| Total facility demand | IT load plus cooling, lighting, resilience systems and other infrastructure |
| Operational demand | The electricity a completed facility uses at a particular time |
| Electricity consumption | The amount of energy used over a defined period |
| Coincident peak demand | The combined demand placed on the network when multiple facilities reach their peaks simultaneously |
Ofgem puts peak Great Britain electricity demand during 2025/26 at approximately 45GW, but uses this to illustrate the scale of the queue. It is not a like-for-like comparison with the requested data centre capacity.
The consultation, titled Curate: Demand Connections Reform, contains two principal measures for data centres.
Ofgem proposes a refundable financial commitment for qualifying projects.
The fee would range from £237,500 to £712,500 per MW, based on 2.5% to 7.5% of an assumed average data centre capital cost of £9.5 million per MW.
The £9.5 million figure is a modelling assumption used by Ofgem. It should not be treated as the verified cost of every data centre development.
The commitment fee would apply to transmission projects and relevant distribution projects of 40MW or more. Ofgem selected that threshold because it says 99% of the capacity currently in the queue relates to projects above 40MW.
Developers could provide the required security through:
The security would remain in place from acceptance of the relevant connection offer until the project is energised.
If the development progresses as a data centre, the fee would be returned at energisation. It could be forfeited if the developer:
Where capacity is reduced, the portion of the fee relating to the removed capacity could become payable. Security for the remaining capacity would then be recalculated.
Ofgem proposes returning forfeited funds to consumers through reductions in Transmission Network Use of System charges.
| Project capacity | At £237,500 per MW | At £712,500 per MW |
|---|---|---|
| 40MW | £9.5 million | £28.5 million |
| 100MW | £23.75 million | £71.25 million |
| 500MW | £118.75 million | £356.25 million |
These are illustrative calculations based on Ofgem’s proposed range. They are not final charges and would not necessarily need to be provided entirely as cash.
Ofgem’s modelling suggests that the financial effect would become more significant for projects with later connection dates.
For a modelled 100MW development, Ofgem estimated a reduction in internal rate of return ranging from 20 basis points for some nearer-term scenarios to 170 basis points for a 2035 connection at the highest proposed fee level using a cash deposit.
The calculation depends on Ofgem’s assumptions and may not reflect the financing structure of individual developments.
The second part of the consultation would require developers to demonstrate that projects are progressing commercially, technically and financially.
The milestones would apply to facilities with a rated IT load of at least 10MW.
Six months after signing a connection agreement, a developer would select one of two routes:
A developer following the lease or sale route would initially need to provide non-binding evidence of interest from a prospective computing customer. This could include heads of terms or a memorandum of understanding.
At a later milestone, developers would need to provide evidence that long-lead electrical equipment is being procured.
Ofgem identifies transformers and switchgear as relevant examples. Evidence could include:
At a further project stage, developers could be required to demonstrate:
The consultation refers to EN 50600, TIA-942 and Uptime Institute Tier certification as possible forms of technical evidence.
For binding computing demand, Ofgem’s current position is to consider evidence covering 20% of capacity for at least one year. That requirement remains open to consultation and has not been finalised.
A developer would be allowed to change its chosen pathway once, followed by a six-month period to provide the relevant evidence.
Failure to meet one of the proposed milestones could result in removal from the connections queue. The consultation does not specify a formal appeals process. Assessments would be undertaken by NESO or the relevant distribution network operator.
A simplified version of the proposed process would look like this:
Projects that fail to meet the proposed evidence requirements could lose their position in the queue.
Requiring evidence of procurement could provide a practical indication that a project is moving beyond an early development concept.
Data centres depend on substantial power and resilience infrastructure, including:
Many of these components must be specified and secured long before installation.
Research cited in Ofgem’s wider supply-chain analysis indicates that transformer lead times have increased by 75% since 2021, while cable lead times have doubled. Other industry evidence puts the average lead time for large power transformers at 128 weeks, with some manufacturers quoting considerably longer periods.
Indicative supply-chain lead times identified in the research include:
| Equipment | Reported lead-time range |
|---|---|
| 132kV transformers | Around 18 months |
| 400kV transformers | Around 24 months |
| Switchgear | Six to 12 months |
| Uninterruptible power systems | 30 to 48 weeks |
| Diesel generators of 2MW or more | 52 to 80 weeks |
These are broad industry indications rather than guaranteed procurement periods. Voltage, specification, manufacturing capacity and market conditions will affect individual orders.
Early procurement may demonstrate commitment, but it also introduces risk. Equipment could need to be ordered before planning, finance, customer agreements and final connection arrangements are fully resolved.
Ofgem’s proposals are intended to remove non-viable developments from the queue, but “speculative” should not automatically be read as fraudulent.
A project may lack delivery certainty because:
There are also legitimate reasons for applying at an early stage.
Developers often need connection certainty before investors, computing customers and equipment suppliers will commit. Long connection lead times can make an early grid application commercially necessary, even while other parts of the development remain unresolved.
This creates one of the central tensions within Ofgem’s proposals.
Several legal commentators have highlighted a potential circularity in the proposed milestones.
A developer may need a credible connection date before a computing customer will sign a binding agreement. The developer may then need that agreement to retain its grid position.
Vinson & Elkins describes this as a dependency loop where financing depends on the connection date, while connection certainty depends on financing. Watson Farley & Williams identifies a similar “chicken and egg” problem between customer commitments and grid access.
The effect may differ by business model.
A large organisation planning to operate its own facility may already have the end use, balance sheet and technical resources needed to demonstrate progress. An independent developer intending to lease capacity could face greater difficulty securing customers before the electricity connection is sufficiently certain.
“We’re consulting on stronger requirements to ensure projects demonstrate real commitment before securing scarce network capacity.”
Eleanor Warburton, Director for Energy System Design and Development, Ofgem, 29 July 2026.
There appears to be broad support for making the grid queue more credible, but the size and structure of the proposed fee have attracted concern.
techUK welcomed the principle of reform and described the connections queue as one of the most significant barriers to UK data centre development. However, the association warned that the proposed commitment fee risks making the UK less attractive as an investment destination.
Legal analysis has also identified concerns about:
Watson Farley & Williams argues that large hyperscalers and infrastructure funds may be better able to absorb the financial commitment than independent developers or joint ventures.
Vinson & Elkins warns that the proposed security could consume borrowing capacity otherwise available to fund construction.
These remain stakeholder predictions. The actual effect will depend on the final fee, accepted forms of security, implementation date and treatment of existing projects.
Connection delays are already encouraging some developers to investigate alternative energy arrangements, including:
Legal commentators have suggested that a substantial commitment fee could increase interest in these options, particularly among developers seeking greater control over their electricity supply and development timetable.
These approaches bring their own challenges. Developers must finance and operate additional infrastructure, while gas-fired power could create tension with energy-efficiency and decarbonisation objectives.
Ofgem’s consultation does not provide a detailed assessment of how the proposed measures could affect behind-the-meter development.
The data centre consultation forms part of Ofgem’s wider Curate, Plan, Connect programme.
Identify projects with credible evidence of progress and remove or deprioritise those that do not meet the requirements.
Create a more realistic picture of future electricity demand so network investment can be planned more effectively.
Improve connection outcomes for developments that are ready and able to proceed.
The approach follows the TMO4+ reforms introduced for generation and storage projects in June 2025. Those reforms moved the system away from a simple first-come, first-served model towards project readiness and strategic alignment.
NESO’s reformed queue, published in December 2025, included 283GW of generation and storage projects and approximately 100GW of transmission-connected demand. More than 300GW of projects were deprioritised after failing to meet the relevant criteria.
The data centre proposals would apply a similar principle to large electricity users. A connection position would need to be supported by evidence that the development is moving towards delivery.
Yes, under the current proposals.
Ofgem envisages applying the measures to existing and future connection offers, although some transitional protections are proposed.
These include:
The implementation date has not been confirmed.
Stakeholders are expected to argue that some or all of the measures should apply only to future projects, particularly where investment decisions were made under the existing arrangements.
London and the Thames Valley remain the largest established UK data centre market, accounting for an estimated 75% to 80% of UK colocation capacity. Slough is the densest cluster within that market.
The area also faces severe connection constraints, with lead times in west London and Slough reported at more than 10 years in some cases.
This is encouraging developers to consider locations outside the established market, including:
The Government has designated AI Growth Zones intended to support data centre and computing infrastructure. A 720MW campus has also been proposed at Cambois in Northumberland.
New locations may offer land, electricity generation and economic incentives, but they can also face constraints involving:
A more credible connections queue could help clients, contractors and suppliers plan against developments with stronger evidence of delivery.
It would not remove the underlying infrastructure challenge.
A mature data centre programme still requires land, planning, finance, customers, network capacity, technical design, equipment and workforce capability to progress together.
Relevant capability includes:
Data centre delivery also requires:
Once operational, facilities require:
Data centre demand does not exist in isolation. Employers compete for many of the same specialists needed by grid programmes, energy projects, advanced manufacturing and other forms of critical infrastructure.
The IET’s 2025 skills survey found that 76% of engineering employers were struggling to recruit for key roles. Separate data centre research cited by JLL indicated that 46% of operators had difficulty finding qualified candidates.
Demand is particularly strong for power-network design engineers, commissioning engineers, project managers, installers, electricians, cable jointers and senior authorised persons.
Developing a fully qualified power networks engineer can require between three and seven years of post-university experience, placing a natural limit on how quickly supply can respond to increasing demand.
The consultation remains open until 16 September 2026.
Ofgem is seeking responses from organisations including:
Ofgem expects to make decisions later in 2026 but has not confirmed an implementation date.
The final measures may differ from those currently proposed, particularly around:
Britain’s data centre connection queue demonstrates the scale of interest in new digital infrastructure, but reserved electricity capacity alone does not make a project deliverable.
A credible development must align its commercial case, planning, electrical design, equipment procurement, construction programme and workforce strategy.
If Ofgem’s reforms produce a more realistic pipeline, employers and contractors could gain a clearer basis for planning capability around projects with stronger prospects of progressing.
That planning will need to begin early. Long equipment lead times and sustained competition for high-voltage, commissioning, project controls and technical delivery professionals mean workforce requirements cannot wait until main construction is ready to begin.
Ofgem is consulting on a refundable commitment fee for qualifying projects and three new progress milestones. The milestones would require evidence of prospective customers, long-lead procurement, financial capability and technical competence. The proposals are not yet in force.
The proposed fee ranges from £237,500 to £712,500 per MW, based on 2.5% to 7.5% of an assumed project capital cost of £9.5 million per MW. It would apply to qualifying projects of at least 40MW.
The security would be returned at energisation if the project proceeds as a data centre. It could be forfeited if the developer terminates the agreement, reduces capacity or changes the development away from data centre use.
No. The figure represents connection capacity associated with projects in the queue. It does not mean every project will be constructed or that completed facilities would use 80GW simultaneously.
Under the proposals, failure to meet one of the new data centre milestones could result in removal from the connections queue. The consultation does not specify a formal appeals process.
Under the consultation, the reforms could apply to existing and future connection offers, subject to specified exemptions and grace periods. The final transitional arrangements have not yet been decided.
The consultation closes on 16 September 2026. Ofgem expects to make decisions later in 2026, but no implementation date has been confirmed.
Primary and supporting sources used in the research include: